Why Does a Main Contractor Refuse to Approve Additional Works?#
During construction projects, changes in design, technical requirements, or project specifications may require work beyond the original contractual scope.
A subcontractor may perform these additional works based on instructions from the main contractor, site engineer, or consultant, expecting their value to be included in subsequent payment certificates.
However, disputes arise when the main contractor refuses to approve the additional works, excludes their value from payment certificates, or argues that the work was already included in the original contract.
In such situations, proving that the work was completed is not enough. The contractor must also establish why the work was required, who requested or authorized it, whether it was approved, and how its value was calculated.
1. How Can You Distinguish Additional Works from Original Contractual Works?#
The first step is to determine whether the disputed work falls outside the original contractual scope.
Additional works may include:
New activities not included in the original bill of quantities.
Modifications to approved designs or technical specifications.
Increased quantities beyond the agreed contractual amounts.
Variations resulting from instructions issued during project execution.
Additional work required due to changes in project requirements.
This distinction is important because the contractual and legal basis for claiming payment may differ depending on the nature of the work.
Simply describing an activity as additional work does not automatically establish an entitlement to separate payment. The contract, its attachments, technical specifications, and variation procedures must all be examined.
2. What Documents Can Prove Additional Works?#
The strength of a claim largely depends on the quality of its supporting documentation.
The following documents are particularly important:
A. Construction Contract and Bill of Quantities
The original contract establishes the agreed scope of work and provides the starting point for assessing additional work claims.
Important documents include:
Contractual scope of work.
Approved drawings and technical specifications.
Bill of quantities and agreed rates.
Variation and change-order provisions.
The consultant's and engineer's approval authority.
Payment certificate and claim submission procedures.
These documents help determine whether the disputed work falls outside the original contractual obligations.
B. Variation Orders and Written Instructions
Variation orders are among the most important supporting documents, particularly when they identify the additional work, its location, the requesting party, and the date of instruction.
Supporting evidence may include:
Approved variation orders.
Letters issued by the main contractor.
Instructions from the engineer or consultant.
Meeting minutes discussing additional works.
Technical approvals and correspondence concerning design changes.
If instructions were issued verbally, subsequent correspondence confirming those instructions or referring to the work performed may provide supporting evidence. Such instructions should be documented as soon as possible.
C. Work Acceptance Certificates and Site Reports
Site records and acceptance documents can help establish that the work was actually performed and identify when and where it took place.
Relevant documents include:
Work inspection and acceptance certificates.
Site engineer reports.
Consultant supervision reports.
Daily site records.
Inspection requests.
Relevant technical testing records.
D. Photographs, Videos, and Execution Records
Photographs and site records may provide supporting evidence of completed work, particularly when they are dated and linked to specific project locations and work items.
Contractors should retain photographs taken before, during, and after execution and connect them to relevant site reports, drawings, and correspondence.
E. Payment Certificates, Invoices, and Financial Claims
These documents help demonstrate that the contractor formally requested payment for the additional work and submitted it for review or approval.
Important records include:
Submitted payment certificates.
Quantity measurement sheets.
Invoices.
Detailed financial claims.
Rejection or exclusion comments.
Proof of submission and receipt.
3. How Can You Establish the Value of Additional Works?#
Proving that additional work was performed does not automatically resolve the question of its financial value.
The main contractor may acknowledge that the work was completed while disputing the quantities, rates, or calculation method.
A detailed technical and financial statement should therefore include:
A description of each additional work item.
The work location and execution date.
The actual quantities completed.
The agreed unit rate, where available.
Material, labor, and equipment costs, where relevant.
The contractual or documentary basis for the proposed rates.
The total amount claimed.
Any amounts previously approved or paid.
Submitting a detailed breakdown rather than a single total figure makes the claim easier to review and assess.
4. What Should You Do If the Main Contractor Refuses to Approve the Payment Certificate?#
If the main contractor rejects the additional works or excludes them from the payment certificate, a structured response is essential.
Step 1: Request Written Reasons for Rejection
Ask the main contractor to identify the disputed items and explain whether the objection relates to execution, quantities, pricing, or the absence of prior approval.
Step 2: Review the Contractual Requirements
Check the contractual procedures and deadlines for submitting claims and objections. Also identify who has the authority to issue instructions and approve variations.
Step 3: Resubmit a Detailed Claim
Connect each additional work item to the relevant supporting documents, including execution records, quantity measurements, payment certificates, and correspondence.
Step 4: Submit a Formal Contractual Notice
Send an official written claim explaining the additional works, their value, the basis of entitlement, and the supporting documentation.
Maintain evidence of the submission date and receipt.
Step 5: Preserve Evidence and Avoid Premature Settlement
Keep original documents, electronic correspondence, and site records.
Do not sign a final release, settlement, or document containing a waiver of claims without reviewing its legal consequences.
5. What Is the Legal Position on Additional Works Under Egyptian Law?#
Where a construction dispute is governed by Egyptian law, the Egyptian Civil Code No. 131 of 1948 contains provisions regulating construction contracts and certain circumstances involving additional works and payment.
Several provisions are particularly relevant.
Article 657 of the Egyptian Civil Code
This article addresses lump-sum and unit-price construction arrangements in specific circumstances where execution of the agreed design requires a substantial increase beyond the estimated quantities.
It requires the contractor to notify the employer promptly, explaining the expected increase in price. Failure to provide the required notice may affect the contractor's right to recover expenses exceeding the estimated amount.
The provision also addresses the employer's right to withdraw from the contract where the necessary increase is substantial, subject to the contractor's entitlement in respect of completed work under the applicable contractual conditions.
The distinction between increased quantities required to execute the agreed design and entirely new or modified works requested during execution is important. Their contractual and legal treatment may differ.
Article 656 of the Egyptian Civil Code
This provision establishes that payment is generally due upon delivery of the work, unless the agreement or applicable custom provides otherwise.
Its application must be considered alongside the project's payment certificate arrangements, acceptance procedures, and contractual payment terms.
Article 658 of the Egyptian Civil Code
This article is particularly relevant to lump-sum construction contracts based on an agreed design.
It generally provides that a contractor is not entitled to additional payment merely because the design is modified or additional work is added, unless the modification results from the employer's fault or was authorized by the employer with an agreement on the additional compensation.
The article also addresses the requirement for a written agreement concerning the additional payment, subject to the circumstances specified in the statutory provision.
Therefore, completing additional work does not automatically establish an entitlement to extra payment in every case. The contract type, reason for the modification, authorization, agreement on compensation, and available evidence must all be examined.
Articles 661 and 662: Subcontracting Arrangements
These provisions address certain aspects of subcontracting.
Article 661 permits a contractor to subcontract all or part of the work unless prohibited by the contract or restricted by the personal nature of the required performance. The main contractor remains responsible to the employer for the subcontractor's work.
Article 662 provides subcontractors with a right, under specified conditions, to bring a direct claim against the employer within the limits of the amount owed by the employer to the main contractor when the claim is filed.
This does not mean that a subcontractor can automatically claim all outstanding payments directly from the project owner. The statutory requirements, applicable limits, and direct subcontracting agreement must be examined.
6. When Do You Need Specialized Legal Assistance?#
Legal review becomes particularly important when:
The main contractor denies issuing instructions for additional works.
Payment certificates are rejected despite supporting execution records.
There is a dispute over the authority of the person who instructed the variation.
The contract imposes strict prior approval or notification requirements.
The parties disagree over quantities, rates, or valuation methods.
Unpaid amounts accumulate and affect project cash flow.
The project is approaching final handover or settlement.
In these circumstances, submitting another payment claim may not be sufficient. The contractual position and available evidence should be assessed to determine whether negotiation, settlement, or formal legal proceedings are appropriate.
7. How Can Legal Review Help Protect Your Construction Payment Claims?#
Construction disputes involving additional works require an understanding of contractual obligations as well as the technical and financial aspects of the project.
Through specialized construction contract drafting and dispute management services, legal assistance may include:
Reviewing construction contracts and identifying the original and additional scope of work.
Examining variation orders, correspondence, and meeting minutes.
Assessing whether the available documents support the claim.
Reviewing payment certificates, quantity statements, and financial claims.
Preparing formal legal claims supported by relevant documentation.
Evaluating negotiation, settlement, and litigation options.
Preventive legal review of construction contracts can also reduce future disputes by establishing clear procedures for requesting, approving, pricing, and documenting additional works.
Do Not Let Poor Documentation Put Your Construction Payments at Risk#
A main contractor's refusal to approve additional works does not automatically determine whether the contractor is legally entitled to payment. Equally, the absence of a formal variation order does not necessarily eliminate every possible basis for a claim.
The outcome depends on the contractual provisions, the nature of the additional work, the reasons for its execution, the authorization provided, and the available supporting evidence.
Contractors should maintain clear records of instructions, approvals, execution reports, quantity measurements, and payment certificates, while complying with contractual notification procedures and deadlines.
Request a legal review of your project documents and an assessment of the available options.
An early review of the contract and supporting records can help identify the legal basis of a claim, avoid procedural mistakes, and determine the appropriate course of action.